结合宁德核电站一期汽轮发电机弹性平台施工过程,阐述了汽轮发电机弹性平台施工过程中高支模施工体系、弹簧隔振器安装、高精度埋件施工、清水混凝土施工、大体积混凝土施工等技术难点及采取控制措施,为后续核电站汽轮机运转层平台施工提供参考。
Combined with the construction process of turbogenerator elastic platform for Ningde Nuclear Power Station,elaborated the technical difficulties and control measures during high formwork construction,spring vibration isolator installation,high precision embedded parts construction,fair-faced concrete construction and mass concrete construction,to provide reference for the follow-up construction of turbogenerator elastic platform.