考虑项目网络特征的鲁棒性项目调度缓冲方法比较 被引量:3

Buffer methods comparison in robust project scheduling with project network characteristics
下载PDF
导出
摘要 对两种缓冲方法应用于具有不同网络特征的项目进行了比较分析。首先,生成具有不同网络特征的大量项目实例,分别用两种缓冲方法制定鲁棒性调度计划;然后,采用仿真实验方法模拟在不确定环境下执行所制定的调度计划;最后,通过分析实验结果比较两种缓冲方法所建计划的鲁棒性绩效指标,归纳出缓冲方法的适用性特征。研究表明,追求解鲁棒性的项目调度适用分散缓冲法,追求质量鲁棒性的项目调度要依据项目规模、网络复杂度及不确定性程度的具体情况选择缓冲方法。 The application of two kinds of buffers in various project networks was compared and analyzed.Amount of project examples were generated with different network characteristics,and critical chain centralized-buffered plans and STC scattered-buffered plans were made respectively for those projects.A simulation experiment was set up to simulate the execution of those project plans in different environments.Robust performance indicators of two kinds of buffered plans were compared by analyzing experiment results,so that the applicability features of the two buffers were summarized.The investigation showed that:scatted buffer method was suitable in solution robustness-oriented project;buffer method should be chosen according to the specific circumstances such as project scale,network complexity and uncertainty in quality-robustness-oriented project.
作者 崔南方 赵雁
出处 《计算机集成制造系统》 EI CSCD 北大核心 2015年第1期280-288,共9页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(71271097)~~
关键词 项目调度 鲁棒性 集中缓冲 分散缓冲 网络特征 project scheduling robustness centralized buffer scattered buffer network characteristics
  • 相关文献

参考文献22

  • 1Olivier Lambrechts,Erik Demeulemeester,Willy Herroelen.Time slack-based techniques for robust project scheduling subject to resource uncertainty. Annals of Operation Research . 2011
  • 2M.A. Al-Fawzan,Mohamed Haouari.A bi-objective model for robust resource-constrained project scheduling[J]. International Journal of Production Economics . 2004 (2)
  • 3Willy Herroelen,Roel Leus.The construction of stable project baseline schedules[J]. European Journal of Operational Research . 2003 (3)
  • 4Li Bie,Nanfang Cui,Xiaoming Zhang.Buffer sizing approach with dependence assumption between activities in critical chain scheduling[J]. International Journal of Production Research . 2012 (24)
  • 5TURNER R.The handbook of project-based management. . 2008
  • 6NEWBOLD R C.Project management in the fast lane:applying the theory of constraints. . 1998
  • 7ROEL LEUS,WILLY HERROELEN.Stability and resource allocation in project planning. IIE Transactions . 2004
  • 8HERROELEN W.Project and production scheduling. . 2007
  • 9Juite Wang.Constraint-based schedule repair for product development projects with time-limited constraints[J]. International Journal of Production Economics . 2004 (3)
  • 10Luong Duc Long,Ario Ohsato.Fuzzy critical chain method for project scheduling under resource constraints and uncertainty[J]. International Journal of Project Management . 2007 (6)

二级参考文献56

共引文献201

同被引文献46

引证文献3

二级引证文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部