摘要
本项目为现有合流污水治理一期系统的续建工程 ,采用化学生物絮凝强化一级处理工艺 ,以去除磷和悬浮及胶体状污染物为主 ,悬浮固体去除率 6 0 % ,总磷去除率 75 % ,处理尾水深水排放长江口 ,可减少排入水体的污染负荷 ,保护长江水质 ,远期预留生物滤池工艺 。
As the continuation to the existing Shanghai Combined Sewerage Works Phase 1, it adopts chemico biological flocculation strengthened primary treatment process to remove phosphorus, soliquoid and colloid contaminants with suspended solid and total phosphorus removing ratios of 60% and 75% respectively. To reduce pollution load in water body and protect water quality of the Yangtze River, the tail water after treatment will be discharged in deep water at the Yangtze River estuary. Biological filter is reserved for future.
出处
《中国市政工程》
2003年第1期45-47,共3页
China Municipal Engineering
关键词
上海
竹园第一污水处理厂
化学生物絮凝
污泥回流
空气搅拌
生物滤池
urban sewage treatment plant, strengthened primary treatment, chemico biological flocculation, sludge back flow, pneumatic homogenization