摘要
以降低运输风险为目的 ,采取可靠的措施 ,对我国岭澳核电站 2个压水堆共 6个自重
Reliable,low risk measures are taken to complete the site transportation of six steam generators of 380 tons weight at the Ling ao Nuclear Power Plant in China.
出处
《起重运输机械》
北大核心
2003年第3期41-43,共3页
Hoisting and Conveying Machinery
关键词
核电站
蒸汽发生器
运输
nuclear power plant
steam generator
transportation