摘要
提出了风险储备金的概念、思路和计算方法,来提高我国水电行业投资风险管理水平。在对国内若干水电工程投资数据资料进行统计分析的基础上,总结出其中存在的数值统计规律,提出了"成本均衡性"和"成本相关性",并用来改进风险储备金的计算精度,提高风险储备金措施的实用价值。
Contingency reserve is introduced to response risks in projects. The key issue is how to estimate the quantity of the reserve. To help the ratiocinating and estimating of the reserve, some principles of variation between the original estimate and the final cost were found on the basis of statistically analyzing the investments of some built hydraulic engineering project. The cost proportion and cost correlation were brought forward, which can highly improve the precision and utility of contingency reserve to response risks involved in the investment of hydraulic engineering project.
出处
《水力发电》
北大核心
2003年第3期1-5,共5页
Water Power