摘要
针对捣固侧装煤焦炉煤塔钢筋混凝土结构漏斗内空间狭小等问题 ,并结合工程实例 ,介绍了其施工方案。该方案针对性强 ,便于操作 ,加强了施工的过程控制 ,保证了工程质量。
According to the complicated problems exited in special situation calculation of aerated concrete with hyperbolic type in funnel of coal coke oven with reinforced concrete structure the construction method of this kind of aerated concrete is introduced based upon engineering example. This method is convenient in operation, which can intensify the construction process control to ensure the engineering quality.
出处
《山西建筑》
2003年第3期209-210,共2页
Shanxi Architecture
关键词
双曲线
混凝土砌块
过程控制
放样
hyperbolic curve, aerated concrete, process control, lofting