摘要
对大连台山热电厂拟采用的增压流化床燃烧联合循环(PFBC-CC)热电联供系统方案进行了分析介绍,并对影响系统热力学性能的参数如辅助过程空气、过量空气、PFB床温、脱硫效率、Ca/S摩尔比等进行了探讨。
The pressurized fluidized bed combined circulation cogeneration of heat and power to be adopted at Taishan thermal power plant ,Dalian is described,and such factors having effect on system thermal mechanics as process air,excess air,PFB temperature,desulphurization efficiency and Ca /S mole ratio,are analysed.
出处
《黑龙江电力》
CAS
2003年第1期20-21,共2页
Heilongjiang Electric Power
基金
国家基础研究发展规划(973)基金资助项目(G199902210533)。
关键词
增压流化床
联合循环
计算
性能分析
过剩空气系统
pressurized fluidized bed
combined circulation
calculation
performance analysis
coefficient of excess air