摘要
莱钢锻压厂 3 5 /6k V降压站控制系统采用 CSC-2 0 0 0型分布式变电站综合自动化系统 ,主要由变压器单元、线路单元、中央单元、监控主站等部分组成。具有自动监视、管理、协调、控制和保护功能 ,可提高系统可靠性和控制水平 ,提高企业经济效益。
The CSC-2000 distributed integrate automatic system is used in the controlling system of 35/6kV substation at the Forging Plant of Laigang. The system is composed of the parts of transformer, wiring, CPU, supervisory control station and so on, and has functions such as automatic monitoring, management, matching, controlling and protecting. It can improve the dependability and control level of the system, and can increase benefits of the enterprise.
出处
《山东冶金》
CAS
2003年第1期26-27,共2页
Shandong Metallurgy