摘要
石头河水电站CT-40调速器在运行中存在较多问题,应用全新的强驱动、力反馈集成式电液随动系统对其进行了改造,改造后的调速器性能优异,技术成熟,改造费用合理。
CT-40 speed governor has many problems in the operation of Shitouhe Hydropower Station. The new driving power feed back integrated electrohydraulic following system is applied . The retrofitted speed governor has better performance, matured technique and reasonable cost.
出处
《西北电力技术》
2003年第1期42-44,共3页
Northwest China Electric Power