摘要
针对某现浇框架的施工 ,由于工期比较紧 ,常规施工无法完成的情况 ,阐述了采用模板预装及梁的钢筋整体入模的施工方法 ,减少了因交叉施工占用的工期。
According to short limit time of the construction of cast in place frame the construction method of formwork pre installation and reinforcement integral installation before concrete pouring is adopted to reduce construction time caused interlace process. At last the construction procedures questions are emphasized.
出处
《山西建筑》
2003年第4期71-72,共2页
Shanxi Architecture
关键词
现浇框架
模板
预装
梁
钢筋
整体入模
平行作业
施工
cast in place frame, pre installation, integral installation, hoisting, parallel operation