长沙市第八水厂的设计与运行 被引量:3

Design and Operation of Changsha No.8 Water Plant
下载PDF
导出
摘要 长沙市第八水厂净水工艺采用折板絮凝反应、平流沉淀和气水反冲滤池,并对絮凝池和沉淀池出水进行了收集、贮存、调节、浓缩、离心机脱水处理。全厂采用了DCS自动监控系统。输配水管网采用了球墨铸铁管和钢管。运行两年多来出水完全符合《城市给水工程规划规范》GB50282-98附录A中规定的生活饮用水一级标准和《生活饮用水水质卫生规范》(2001)要求。 The water cleaning process in Changsha No.8 Water Plant uses flap flocculation reaction,advection sedimentation and air water backflush filter tank,and the outlet water from the flocculation tank and sedimentation tank is collected,stored,adjusted,thickened and dewatered through a centrifuge.DCS automatic monitoring and controlling system is used for the whole plant.Graphite cast iron pipes and steel pipes are used for the water supply and distribution pipe network.In the past more than two years since the process was put into operation,the quality of the effluent water has been completely conforming to the standard for first grade domestic drinking water specified in Appendix A to Code for Planning of Municipal Water Supply Works (GB50282 98) and meeting the requirements of Hygienic Specification for Quality of Domestic Drinking Water (2001).
作者 周健
出处 《工业用水与废水》 CAS 2003年第2期24-26,共3页 Industrial Water & Wastewater
关键词 长沙市第八水厂 设计 运行 净水工艺 折板絮凝反应 平流沉淀 气水反冲滤池 自来水 给水处理 portable water feed water treatment water taking cleaning pipe network flocculation sedimentation
  • 相关文献

同被引文献23

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部