摘要
本文以晋煤集团亿欣煤业盘区变电所巷道为研究对象,该巷道在使用过程中出现两帮破碎、底鼓严重,变形量大等现象,严重影响该巷道的使用,实践证明,传统的锚网索加强加固措施不能有效控制巷道变形,采用对巷道围岩变形区域按照底板加固、顶帮连体支护、顶板二次注浆的方法依次进行治理,取得了良好治理效果。
in this paper the jin coal group hin a panel of coal roadway as the research object, the substation in the roadway in the process of using the two broken, severe floor heave, such as large deformation phenomenon, the serious influence the use of the roadway, practice has proved that traditional anchor wire rope strengthening reinforcement measures cannot effectively control the deformation of roadway, the area of roadway surrounding rock deformation in accordance with the slab reinforcement, top help conjoined supporting and top secondary grouting method in management, has obtained the good management effect.
作者
牛刚强
NIU Gangqiang(Shanxi Jincheng Anthracite mining group co.,ltd Jin sheng yi xin coal industry ,Jincheng 048019 , China)
出处
《煤矿现代化》
2019年第2期101-103,共3页
Coal Mine Modernization
关键词
围岩变形
应力集中
围岩监测
治理效果
Surrounding rock deformation
Stress concentration
Surrounding rock monitoring
Governance effect