摘要 文章介绍旋转竖立井架、吊车竖立井架、异地组装整移井架和桅杆单向依次竖立等四种方案的施工步骤和优缺点。 based on the characteristics of interconnection and cross-construction of three types of project(drilling of freeze holes and walling of freeze cellar and shaff collar by mine construction department; building of winder house and winder foundation by the civil engineering department; installation of shaft sinking facilities by electrical and mechanical engineering department) in the initial period of shaft sinking in Huaibei mine area, the headframe group should install the sinking headframe and other sinking equipment in the shortest time when the shaft site, capacity of lifting equipment and tools and technical quality of the workers are permissible. It describes in detail steps of erection and analyzes the merits and demerits of each method.
作者 王吉德
出处 《煤炭科学技术》 CAS 1988年第5期41-43,63-64,共5页 Coal Science and Technology
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部