摘要
顺溪水库工程拱坝左岸坝肩165.00m高程存在F1断层,本文阐述了该部位坝肩稳定复核成果及该部位断层技术处理的方法,通过对监测数据分析,表明该处理措施满足大坝安全运行要求。
Shunxi Reservoir Project arch dam left bank dam abutment is provided with F1 fault in elevation 165. 00 m. In the paper,dam abutment stability review results in the part and fault technical treatment methods in the part are described.It is obvious that the treatment measures can meet requirements of dam safety operation through analyzing monitoring data.