引黄工程地下泵站水锤防护设计 被引量:1

Design on water hammer protection for underground pump station of Wanjiazhai Yellow River Diversion Project
下载PDF
导出
摘要 引黄工程总干线一、二级泵站串联运行 ,设计布置D =12 0m的进、出水调压井于一级泵站进、出口 ,二级泵站进口 ,在一、二级泵站之间的 4 # 有压隧洞上设置水工建筑物作为水锤防护主要措施 ,通过系统水力过渡过程计算分析 ,验证了建筑物设计的合理性。 The type of operation in series of the No.1 and No.2 pump stations on the main line of Wanjiazhai Yellow River Diversion Project is adopted.As the main measures of water hammer protection,three surge tanks with the diameter of 12 metre each are employed ,of which two are arranged at the inlet and outlet of the pump station No.1,and one at the inlet of the pump station No.2.Besides above mentioned surge tanks,one escape well is constructed on the pressure tunnel between two pump stations for the same purpose.The reasonability of the layout of these hydraulic structures was verified by means of calculation and analysis on the procedure of hydraulic transition of this system.
作者 陈洪莲
出处 《水利水电工程设计》 2003年第2期1-3,共3页 Design of Water Resources & Hydroelectric Engineering
关键词 引黄工程 地下泵站 水锤防护 设计 调压井 溢流 隧洞 水工建筑物 pump station,operation in series,water hammer protection,surge tanks,overflow,procedure of hydraulic transition,Wanjiazhai Yellow River Diversion Project.
  • 相关文献

参考文献2

  • 1刘竹溪 等.泵站水锤及其防护[M].北京:水利电力出版社,1985.31-52.
  • 2段乐斋 主编.水利水电工程地下建筑物设计手册[M].成都:四川科学技术出版社,1993..

共引文献6

同被引文献14

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部