针对黄梅山铁矿甄山凹尾矿坝浸润线埋深浅 ,尾矿坝安全性差的状况 ,开展了水平滤管和滤水碎石坑排水降低浸润线的治理 ,工程实施后 。
In view of the small depth of the seepage line and poor safety of Zhenshanwa tailings dam at Huangmeishan Iron Mine,the engineering treatment for lowering the seepage line by horizantal pipe and water filtering gravel pit for water discharge was carried out, the seepae line being remarkably lowered.
出处
《金属矿山》
CAS
北大核心
2003年第6期63-64,共2页
Metal Mine
关键词
水平滤管
滤水碎石坑
尾矿坝
降水
浸润线
铁矿
Seepage line,Tailings dam,Horizontal filter pipe,Water filtering gravel pit