碾压混凝土重力坝施工期温度场研究 被引量:5

Study on Temperature Field of Roller Compacted Concrete Gravity Dam during Construction
下载PDF
导出
摘要 根据碾压混凝土重力坝的施工特点,提出用国际通用大型有限元软件Ansys进行大坝施工期温度场仿真,并介绍了实现过程。典型碾压混凝土重力坝的施工期温度场仿真计算结果表明,浇筑温度及外界气温对坝体温度均有显著影响,碾压混凝土自然降温速度缓慢。 In this paper, Ansys software, a world wide popular common software used in finiteelement analysis, is suggested to simulate the temperature field of roller compacted concrete gravity dam during construction. According to a scheduled timetable of construction, temperature fields of a typical RCC gravity dam within construction period under several different construction conditions are calculated by simulating the layer constructing of the dam. The temperatures of placed RCC and air effect heavily on the temperature field of dam.
出处 《水电能源科学》 2003年第2期31-34,共4页 Water Resources and Power
关键词 碾压混凝土 重力坝 施工期 温度场 roller compacted concrete gravity dam construction period temperature field
  • 相关文献

参考文献1

  • 1嘉木工作室.ANSYS 5.7有限元实例分析教程[M].北京:机械工业出版社,2001..

同被引文献20

引证文献5

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部