摘要
以新善家峁 2号隧道工程施工为例 ,介绍了其施工方案的选择及实施过程 ,经监挖量测 ,实现了安全进洞。指出提供准确的洞口地质、地形、地貌情况 。
Taking the Xinshanjia'ao 2# tunnel construction work as example the construction schemes' selection and implementation process are introduced. Based upon monitoring excavation and accurate measuring safe entrance is realized. Author emphasized that the accurately analysis of geological and geo morphologic situations of tunnel entrance is premise of proper construction.
出处
《山西建筑》
2003年第6期242-243,共2页
Shanxi Architecture