摘要
转炉烟道因制造存在误差,导致在安装过程中无法满足设计要求。通过对烟道支腿及法兰面的局部现场调整,解决了此问题。
Mounting of the converter flue could not meet the needs of design because of deviation in manufacturing of the flue. Therefore, the support foot and part of the flange surface were adjusted in situ, which solved the problem.
出处
《冶金动力》
2003年第3期20-21,共2页
Metallurgical Power