全面介绍了葛洲坝和南桥换流站12年来一次绕组类设备的运行情况,着重分析了绕组类设备故障导致直流系统被迫停运的原因,并提出了防止类似事故发生以及消除现有设备缺陷的技术措施与建议。
This paper summarizes the operation conditions of primary equipments with winding in 12 years in Gezhouba and Nanqiao HVDC Converter Stations.The reasons of the forced outrage for HVDC transmission system, which are caused by the faults of primary equipments with winding,are also analyzed in the paper.
出处
《电力设备》
2003年第3期10-14,共5页
Electrical Equipment