七台河电厂350MW汽轮机组的启动特点 被引量:2

Starting - up characteristics of 350 MW turbine power generating set at Qitaihe power plant
下载PDF
导出
摘要 分析了七台河电厂美国GE公司270T367-8型汽轮机与HG-1170/17.4-YM1型锅炉配合的启动特点,高压缸启动和中压缸启动,包括启动过程中转子预暖、阀腔预暖、冲动转子时的参数选择过程以及机炉参数匹配问题,具有启动时间短、操作方便等特点。 The starting - up characteristics of GE - made 270T367 - 8 turbine in conjunetion with HG-1170/17.4 - YMl steam boiler,high - pressure cylinding starting - up and mediam pressure cylinder starting - up, including preheating of rotor and preheating of valve chamber during starting - up,selection of parameters while the rotor is being driven, and the matching of gonerator and boiler parameters,which feature short start - up time and easy operation, are discussed in detail.
出处 《黑龙江电力》 CAS 2003年第3期219-222,共4页 Heilongjiang Electric Power
关键词 预暖 冲转 旁路 汽轮机 高压缸启动 中压缸启动 preheating driving of rotor bypass steam turbine high - pressure cylinder starting - up medium - pressare cylinder starting - up
  • 相关文献

同被引文献2

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部