摘要
某动力厂 12 0m高混凝土烟囱采用滑模施工 ,在 73 3~ 97 7m标高处 ,烟囱中心偏差严重超标 ,造成质量事故。在事故处理过程中 ,利用原有滑模体系将该段混凝土壁顺利拆除 。
The concrete chimney with a height of 120 meters for a power plant adopted slipform construction. Because the central deviation went far beyond the limit, quality failures occurred in the section from 73 3m to 97 7m. To deal with such problem, the concrete wall was removed successfully by the exiting slipform system and some relevant measures was taken so that the quality of construction was guaranteed.