针对本钢 2× 2 65m2 烧结机成品矿输送流程设计不合理而导致的烧结机频繁停机 ,通过采取合理的改进措施 ,实现了不停机倒料线 ,有效地提高了烧结机作业率和烧结矿产量 ,同时 。
Because of the design faults of sinter product conveying flowsheet in BENGANG 2×265?m 2 sintering machine system,the unscheduled shutdown takes place frequently By modifying the product conveying route,the down time was reduced greatly and the sinter output was increased