介绍网络计划技术在马鞍山市某企业制定技改施工计划中的应用研究 ,原测算技改施工需 14 5天 ,利用网络计划技术 ,对关键路线进行压缩 ,实际完工期为 12
Technique of network program is applied to planning scheme of construction of technique reform, made by Enterprises at Maahshan city. The key lines have been pressuring by technique of network program. Based on above, Technique reform period is from original 145 days to actual 122 days.