摘要
介绍了大源渡水电枢纽工程纵堰拆除爆破中所采取的减震措施 ;对爆破过程进行了动态监控。试验表明 ,爆破震动监测可以及时反馈信息 ,指导设计与施工 ,有助于工程施工安全。
It is described of the vibration-reduced measures in controlled blasting for dismantling the longitudinal weir of Dayuandu key hydropower project. The dynamical monitoring is carried out for the blasting process. The test has shown that the monitoring of blasting vibration can feed back information timely to guide the design and construction and guarantee the safety in construction.