摘要
阐述了新型钻孔挤压分支桩在阜阳商厦三期工程中的成桩工艺及施工中的分支、孔底沉渣、钢筋笼上浮等方面对成桩质量的影响和控制。
The pile technology of new-type branch pile applied in the third construction stage of Fuyang Market Building is introduced in this paper. It was found that the pile quality is affected by the factors like branch,hole bottom residue,floatability of the reinforcing cage,and so on.
出处
《岩石力学与工程学报》
EI
CAS
CSCD
北大核心
2003年第8期1390-1392,共3页
Chinese Journal of Rock Mechanics and Engineering
关键词
土力学
分支桩
成桩
质量控制
工程施工
soil mechanics,Fuyang Market Building,branch pile,pile,quality control