三峡水利枢纽围堰发电期梯级调度运行方式 被引量:1

Cascade dispatching operation modes of the Three Gorges Project during cofferdam power generation period
下载PDF
导出
摘要 根据三峡水利枢纽工程进度及相关部门的要求 ,就三峡 (围堰发电期 )~葛洲坝水利枢纽联合调度运行中有关泄洪设施的运用调度方式 ,三期围堰安全度汛方案 。 According to the construction progress of the Three Gorges Project and the demands of some departments concerned, this paper fully analyzes four modes of the combined dispatching operation of the Three Gorges Project~Gezhouba hydropower station during cofferdam power generation period, that is, the dispatching mode of flood-releasing structures, the third-stage cofferdam passing safely through flood season, the cascade dispatching mode of power generation, the cascade dispatching mode of navigation and ship lock.
出处 《水力发电》 北大核心 2003年第7期56-59,共4页 Water Power
基金 国家自然科学基金 水利部资助重大项目(5 9890 2 0 0 ) 中国长江三峡工程开发总公司博士后基金资助
关键词 三峡水利枢纽 围堰 梯级水库 联合调度 cofferdam power generation period, Gezhouba hydropower station, cascade reservoir, combined dispatching, economic operation, Three Gorges Project
  • 相关文献

参考文献3

  • 1水利部长江水利委员会编.三峡(围堰发电期)~葛洲坝水利枢纽梯级调度规程编写说明[R].,2003..
  • 2中国长江三峡工程开发总公司.三峡~葛洲坝梯级调度有关专题研究,三峡工程科研项目验收报告[R].,2002..
  • 3中国长江三峡工程开发总公司.三峡~葛洲坝梯级调度有关设计专题研究.三峡工程科研项目合同(CT-02-066-01)[R].,2002..