根据三峡水利枢纽工程进度及相关部门的要求 ,就三峡 (围堰发电期 )~葛洲坝水利枢纽联合调度运行中有关泄洪设施的运用调度方式 ,三期围堰安全度汛方案 。
According to the construction progress of the Three Gorges Project and the demands of some departments concerned, this paper fully analyzes four modes of the combined dispatching operation of the Three Gorges Project~Gezhouba hydropower station during cofferdam power generation period, that is, the dispatching mode of flood-releasing structures, the third-stage cofferdam passing safely through flood season, the cascade dispatching mode of power generation, the cascade dispatching mode of navigation and ship lock.
出处
《水力发电》
北大核心
2003年第7期56-59,共4页
Water Power
基金
国家自然科学基金
水利部资助重大项目(5 9890 2 0 0 )
中国长江三峡工程开发总公司博士后基金资助
关键词
三峡水利枢纽
围堰
梯级水库
联合调度
cofferdam power generation period, Gezhouba hydropower station, cascade reservoir, combined dispatching, economic operation, Three Gorges Project