国产首台450t/hCFB锅炉冷态试验研究 被引量:2

Experimental Research of First Domestic Made 450 t/h Boiler in Cold State
下载PDF
导出
摘要 通过对一、二次风量测量装置的标定试验、炉膛布风板空板阻力试验以及料层厚度为500mm的料层阻力试验,确定风量标定系数及料层阻力曲线,找出临界流化风量,同时检查布风板布风均匀性和有关风机的出力特性,确定冷渣器排渣控制参数,为循环流化床锅炉的稳定、正常运行提供依据。 Through the calibration of primary and secondary air measuring apparatuses,and test of air resistance of air distribution dampers and coal layer resistance at thickness of 500 mm, the air flow calibration coefficient and coal layer resistance curve are determined. The critical fluidizing air flow is found. In addition, the homogeneity of air distribution of the distribution dampers and the output characteristics of related fans are checked, and the slag-removing control parameters of slag cooler are determined. These provide a scientific basis for stable and normal operation of the CFB boiler.
出处 《河北电力技术》 2003年第4期1-3,28,共4页 Hebei Electric Power
关键词 CFB锅炉 冷态试验 研究 风量标定 CFB boiler cold state test research air flow calibration
  • 相关文献

同被引文献11

引证文献2

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部