对 130t h高温高压循环流化床锅炉的调试、运行及试验研究进行了全面的分析总结。重点介绍了冷态试验、热态试验。
This paper indicates debugging and running on 130t/h high temperature and pressure CFB boiler at Zhangzhuang Power Plant.The cold test,the hot test, retrofit of facility and the analysis of running are introduced.