通过分析公伯峡水电站施工渡汛的影响因素,确定龙羊峡水库的运行方式是影响施工渡汛的主要因素。针对龙羊峡水库的实际运行情况,着重研究了龙羊峡水库不同运行方式对公伯峡水电站施工渡汛的影响,给出了合理的渡汛方案。
The factors which affect flood handling during construction period of Gongboxia hydropower station have been analysed and the operation mode of Longyangxia reservoir has been considered as the main factor.Based on the real operation condition of Longyangxia reservoir, the influence of different operation modes of Longyangxia reservoir on flood handling during construction period of Gongboxia hydropower station is has been intensively studied, and the rational scheme has been proposed.