在施工方面,斜井施工的测量放线、运输等比较困难,尤其是混凝土衬砌模的设计和运输更为复杂。白水坑电站采用木模在施工中质量好,效率高,具有很好的经济效益。
In the procedure of construction,the measure and transportation of inclined well construction is difficult,and the design and transportation of concrete- lining match board is especially complex. During the construction of Baishuikeng hydropower station the assembled wood board is used,which is of good quality,high efficiency and good economic returns.
出处
《浙江水利水电专科学校学报》
2003年第3期37-38,共2页
Journal of Zhejiang Water Conservancy and Hydropower College