高混凝土坝蓄水河谷-库坝变形规律 被引量:13

General rules of dam-valley deformation due to reservoir impoundment
原文传递
导出
摘要 本文基于二滩、龙羊峡、李家峡、小湾、锦屏一级、大岗山、溪洛渡、三峡、胡佛(美国)、江垭和铜街子等11座高混凝土坝工程的现场监测数据,研究上下游河谷与库坝受水库蓄水运行引起的变形响应规律。通过综合分析库坝的基本参数、工程水文地质条件以及蓄水后河谷–库坝时空变形的内在关联,重点讨论了库盆沉降与下游河谷竖向变形、谷幅变形以及坝体结构变形的一般性规律。本文研究结果可为相关高坝工程的设计分析与安全监测提供重要参考。 This paper presents an investigation on dam-valley deformation responses to reservoir impoundment by analyzing the field data of 11 high concrete dams,including Ertan,Longyangxia,Lijiaxia,Xiaowan,Jinping I,Dagangshan,Xiluodu,Three Gorges,Hoover(USA),Jiangya and Tongjiezi hydropower projects.We collect and analyze the fundamental design parameters,geological and hydrogeological conditions,and field measurements of dam-valley deformation caused by reservoir impoundment,and reveal several general rules of reservoir settlement and downstream valley vertical movements,valley deformation along horizontal direction,and dam structure displacements.The findings can provide valuable references for the design,analysis,and safety monitoring of high dams.
作者 武明鑫 江汇 张楚汉 WU Mingxin;JIANG Hui;ZHANG Chuhan(China renewable energy engineering institute,Beijing 100120;State Key Laboratory of Hydroscience and Hydraulic Engineering,Tsinghua University,Beijing 100084)
出处 《水力发电学报》 EI CSCD 北大核心 2019年第8期1-14,共14页 Journal of Hydroelectric Engineering
基金 中国长江三峡集团有限公司项目(XLD/2117)
关键词 高混凝土坝 库盘沉降 下游河谷变形 谷幅变形 坝体变形 high concrete dam reservoir basin settlement downstream valley movement valley deformation dam displacement
  • 相关文献

参考文献10

二级参考文献116

共引文献157

同被引文献168

引证文献13

二级引证文献60

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部