以某风力发电项目为工程实例,详细介绍了采用预应力锚栓技术进行风机基础施工,重点对预应力锚栓基础施工工艺、螺栓杆安装精度,上、下锚板水平度控制等进行了描述。
Combining with the project of a wind generator,the foundation construction with pre-stressed anchor bolt is described in detail.The foundation construction process,bolt installation accuracy,horizontal control of top and bottom anchor plates are emphasized described in detail.
出处
《施工技术》
CAS
北大核心
2014年第S1期114-115,共2页
Construction Technology
关键词
风力发电机
基础
预应力锚栓
施工技术
wind generator
foundation
pre-stressed anchor bolts
construction