复合地层下盾构换刀技术研究 被引量:14

The Research of Cutter Changing Technology of Shield Machine in Compound Stratum
下载PDF
导出
摘要 盾构机在复合地层中换刀是一项难度系数较大的危险作业。本文以穗莞深城际轨道交通线隧道工程为背景,针对本隧道工程所处复合地层的特点,通过旋喷桩加固地层的方法,保证了掌子面土体的稳定性,有效地避免了土体因压力差而发生坍塌的事故,成功实现了常压换刀作业,为类似工程的换刀作业提供了重要借鉴。 The cutter changing of shield machine in compound stratum is a hazardous operation of greater degree of difficulty.In this paper,taking the tunnel project of Guangzhou-Dongguan-Shenzhen inter-city rail transit as the background,aiming at the feature of compound stratum of tunnel project,the ground was consolidated by the method of churning pile,and then the stability of the soil of working level was ensured,the accident of soil collapse due to the pressure difference was avoided effectively,the cutter changing at atmospheric pressure was accomplished successfully,which provides important reference for the cutter changing under the similar condition.
出处 《施工技术》 CAS 北大核心 2014年第S1期381-384,共4页 Construction Technology
基金 国家863项目(2012AA041803) 国家自然科学基金项目(51275321) 河北省教育厅项目(YQ2013035)
关键词 复合地层 盾构 换刀 旋喷桩 compound stratum shields cutter changing churning piles
  • 相关文献

参考文献5

二级参考文献18

  • 1郑达,武百良.盾构隧道压气作业施工方法[J].广州建筑,2004,32(4):15-17. 被引量:8
  • 2吴江滨.盾构施工过程中进仓技术若干探讨[J].建筑技术,2006,37(8):587-588. 被引量:4
  • 3陈馈.狮子洋隧道sDⅢ标盾构选型设计与对接施工[C]//中国中铁隧道集团2007年水底隧道专题技术交流大会论文集.河南洛阳:中铁隧道集团有限公司,2007:146-150.
  • 4徐军哲.盾构带压进仓作业工法(3.6bar以内)[C]//中国中铁隧道集团工法专辑.洛阳:中铁隧道集团有限公司,2006.
  • 5郑清君,梁奎生,李凤远,等.狮子洋隧道盾构掘进施工危险源分析及对策[C]//中国中铁隧道集团2008年盾构(TBM)隧道专题技术交流大会论文集.河南洛阳:中铁隧道集团有限公司,2008:62-65.
  • 6[1]刘启山.岩石隧道掘进机(TBM)施工及工程实例[M].北京:中国铁道出版社,2004.
  • 7周文波.盾构法隧道施工技术及应有[M].北京:中国建筑工业出版社,2007:148-151.
  • 8张风祥,朱合华,傅德明.盾构隧道[M].北京:人民交通出版社,2004.
  • 9洪开荣.广深港大断面特长水下盾构隧道的技术难点分析[J].隧道建设,2007,27(6):1-3. 被引量:51
  • 10卢创冕.盾构压气进舱作业技术要点[J].建筑机械化,2008,29(4):51-53. 被引量:8

共引文献106

同被引文献77

引证文献14

二级引证文献61

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部