城市连续钢箱梁施工预拱度研究 被引量:1

Research on Pre-camber of City Steel Box Girder Bridge
下载PDF
导出
摘要 城市钢箱梁桥在施工中要设置施工预拱度,其值是在设计预拱度的基础上考虑很多因素影响,目前多凭经验设置。针对二阶段制造方式的预制架梁法施工,采用简化方法分析了体系转换、支架支座沉降、环口焊接收缩和昼夜温差4种主要因素对钢箱梁挠度的影响,总结了胎架预拱度和临时支架施工预拱度的设置方法,运用该法计算实际工程105m单箱双室钢箱梁桥的施工预拱度,与实际情况吻合较好。 It should set construction camber in the construction of steel box girder bridge,which considered many factors on the basis of camber of design,and made mainly by experience at present. On the two-phase manufacturing way of precast girder construction,this paper uses the simplified method to analyze influence of four main factors to the deflection of steel box girder,which are system transformation,settlement of stents and bearings,welding shrinkage on interface and temperature difference between day and night,and then come to the conclusion of setting method of jig camber and temporary support camber. Uses the method to calculate construction camber of 105 meter's single double room steel box girder bridge and is in accordance with the actual situation.
出处 《施工技术》 CAS 北大核心 2015年第S2期251-253,共3页 Construction Technology
关键词 施工 预拱度 体系转换 焊接 收缩 模拟 温差影响 construction pre-camber system transformation welding shrinkage simulation influence of temperature difference
  • 相关文献

参考文献2

二级参考文献8

  • 1中交公路规划设计院有限公司.JTGD62-2004公路钢筋混凝土及预应力混凝土桥涵设计规范[S].北京:人民交通出版社,2004.
  • 2TB10212--2009,铁路钢桥制造规范[S].
  • 3新建时速300-350公里客运专线铁路设计暂行规定(上、下)[M].北京:中国铁道出版社,2007.
  • 4GB/T5224-2003预应力混凝土用钢绞线[S].北京:中国标准出版社,2003.
  • 5JTG/T 50—2011,公路桥涵施工技术规范[S].
  • 6GB50017-2003.钢结构设计规范[S].[S].,..
  • 7GB50205-2001.钢结构工程施工质量验收规范[S].[S].,..
  • 8JGJS1-2002建筑钢结构焊接技术规程[S].

共引文献6

同被引文献6

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部