呼和浩特国家公路运输枢纽汽车客运东枢纽站-综合站务楼的下部结构为全现浇钢筋混凝土框架结构体系,上部为钢筋混凝土拱和与之连接的钢管拱结构。钢筋混凝土拱为非常规截面,钢筋密度大,结构复杂。简要介绍了钢筋混凝土拱柱的钢筋施工,包括所涉及的支撑体系、模板定位加固、混凝土浇筑等内容。
The substructure of Hohhot Car Passenger Station East Hub Station engineering is system of cast-in-place reinforced concrete frame structure. The upper structure is arch structure. Reinforced concrete arch bridge is a special section.Its steel density is high,and its structure is complexity. This paper introduces the reinforcement construction of reinforced concrete arch,including supporting system,a template positioning reinforcement,concrete pouring and other content.
出处
《施工技术》
CAS
北大核心
2015年第S2期505-507,共3页
Construction Technology
关键词
钢筋混凝土
异形构件
拱柱
施工技术
reinforced concrete
special-shaped components
arch
construction