南昌地铁联络通道水平冻结法施工质量控制 被引量:10

Quality Control in Horizontal Freezing Construction of Connecting Passage in Nanchang Metro Tunnel
下载PDF
导出
摘要 介绍了在富水砾砂层中南昌地铁1号线某区间联络通道的水平冻结法施工质量控制方法。对施工过程中冻结孔施工、冻结运转、温度变化、冻胀融沉以及施工队伍选择及通道开挖条件判定等方面进行了监控,并对实测数据进行了分析。施工效果良好,这表明在地质条件复杂和环境影响要求高的城市地铁联络通道冻结法施工过程中,质量控制很重要。 The quality control of the horizontal freezing methods are introduced to the constructions of connecting passages in Nanchang Metro Line 1 built in complex strata with watered gravel sand. The construction is monitored and the measured data is analyzed in the whole processes of drilling,freezing,temperature changing,frost heaving,thawing settlement,team selection and excavating decisions. The sound effects show the importance of the quality control in constructions of metro tunnel connecting passages to meet with the complicated geological conditions and harsh environmental requirements.
出处 《施工技术》 CAS 北大核心 2017年第S1期717-720,共4页 Construction Technology
基金 国家自然科学基金资助项目(11362016) 江西省自然科学基金资助项目(20151BAB2002001)
关键词 地铁 施工质量控制 联络通道 水平冻结法 富水砾砂层 施工技术 质量控制 subways connecting passage horizontal freezing construction complex strata with watered gravel sand construction quality control
  • 相关文献

参考文献10

二级参考文献34

共引文献239

同被引文献102

引证文献10

二级引证文献52

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部