结合在硬岩中进行地下连续墙成槽施工的各种方法进行分析,总结出在不同岩石强度情况下所采用针对性的成槽设备和工艺,以提高施工效率并降低施工成本。
This paper made analysis combined with various methods for underground continuous wall trench construction in hard rock,summarized the pertinent slot forming equipment and technology under different rock strength conditions to improve the efficiency of construction and reduce the cost.
出处
《施工技术》
CAS
2018年第S1期7-10,共4页
Construction Technology
关键词
硬岩
铣槽机
成槽
铣槽工艺
hard rock
milling machine
groove