摘要
关于硬岩地层中既有隧道喷锚支护受邻近隧道施工影响产生的变形控制标准的研究很少,依托青岛地铁4号线人民会堂站斜井上跨3号线人汇区间工程为背景,采用MIDAS/GTS计算分析斜井施工对既有运营隧道的影响,并结合自动化监测实测数据进行研究,得到以下结论:采用超前小导坑非爆破+后续爆破扩挖减振爆破方案,产生的爆破振动速度满足爆破控制标准0.5cm/s;硬岩地层喷锚永久结构变形控制标准建议为:竖向及水平收敛≤3mm,爆破振速≤0.5cm/s;硬岩地层隧道施工的主要影响区≤0.5H,次要影响区为(0.5~0.8)H。
In order to fill in the blank in research on overlapping bolt&shotcrete tunnel in rock strata,we choosing Qingdao metro line 4 Renmin Huitang station's inclined shaft which overcross the existing bolt&shotcrete tunnel of metro line 3 as background,adopting automatic monitoring,using MIDAS/GTS to numerical simulate the effect of existing tunnel's bolt &shotcrete lining caused by inclined shaft excavation. The FEA and monitoring results indicate that:the speed of blast vibration is controlled into 0. 5 cm/s with the advanced non-blasting heading and subsequent blasting excavation;the deformation standard of bolt&shotcrete lining tunnel in rock strata is recommended as follows: the vertical&horizontal displacement ≤3 mm,the speed of blast vibration≤0. 5 cm/s;the primary influence area of tunnel excavation in rock strata may be adjust to0 ~ 0. 5 H,the secondary influence area may be adjust toea to(0. 5 ~ 0. 8) H.
出处
《施工技术》
CAS
2018年第S1期-,共4页
Construction Technology
关键词
硬岩地层
喷锚支护
数值模拟
自动化监测
爆破减振
影响区
solid rock
combined bolting and shotcrete
simulation
auto-monitoring
blasting vibration
influence area