摘要
为满足栈桥的安全可靠以及自然保护区环保的要求,以新建蒙西至华中铁路26标段华洪运河特大桥钢栈桥施工为例,介绍了跨湖跨境12m钢栈桥的结构设计,并采用MIDAS Civil进行工况模拟,证明了该钢栈桥结构设计合理,施工方法可行。
To meet the safe and reliable of piers and the requirements of environmental protection,nature reserves,based on the new stake to 26 of central China railway Huahong canal steel pier construction of the large bridge as an example,introduces the cross-border 12 m steel trestle design of the approach bridge across the lake,and uses the MIDAS Civil condition simulation,show that the steel trestle design is reasonable,the construction method is feasible and can be used for future similar projects.
出处
《施工技术》
CAS
2018年第S1期1166-1169,共4页
Construction Technology
基金
中体十六局集团有限公司2016年度科技研究开发计划课题(K2016-5C)
关键词
钢栈桥
钢管桩
贝雷梁
设计
施工技术
steel trestle
steel pipe piles
bailey beam
design
construction