移动模架逐孔施工50m现浇梁预拱度测算方法的研究 被引量:2

Research on Pre-arch Measuring Method of 50m Cast-in-situ Beam in Movable Formwork Hole-by-hole Construction
下载PDF
导出
摘要 对移动模架进行预压静载试验测得相应数据,结合青岛海湾大桥设计预拱度、桥梁自身的净挠度通过与移动模架弹性变形的比较计算得出施工立模预拱值,确保施工中箱梁线形符合设计要求。 Pre-ballast static load test data of movable formwork frame are obtained,and the pre-arch value of construction formwork is calculated by comparing the design pre-arch of Qingdao Bay Bridge and the net deflection of the bridge itself with the elastic deformation of movable formwork frame,so as to ensure that the alignment of box girder meets the design requirements in construction.
作者 魏红兵 WEI Hongbing(Bridge&Tunnel Engineering Co.,Ltd.of CCC Fourth Highway Engineering Co.,Ltd.,Beijing 101101,China)
出处 《施工技术》 CAS 2018年第A04期472-474,共3页 Construction Technology
关键词 移动模架 预压静载试验 预应力混凝土结构 预拱度设置 moving formwork prestressed static load test prestressed concrete structure pre-camber setting
  • 相关文献

同被引文献3

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部