摘要
选取典型的小净距隧道洞口浅埋段施工时序,分析地表沉降监测数据并采用FLAC3D施工全过程进行数值模拟,研究隧道左右线洞口段施工时序对隧道地表沉降的影响,现场监控量测数据与数值模拟互为验证,总结典型隧道施工时序中地表沉降的变化特点,为避免施工中出现多个风险部位对施工工序的优化提出建议。
This paper chose the typical construction sequence for the shallow-buried section of the tunnel with small interval,analyzed the data of surface settlement prediction and used FLAC3 D to do numerical simulation during the whole course to study how the construction sequence of the portal section in both sides of the tunnel affect the surface settlement.The data from the on-site inspection and the numerical simulation are verifications for each other.In addition,this paper concluded the change characteristics of surface settlement in the typical construction sequence for tunnels and proposed suggestions to avoid risks during the construction and to optimize the construction sequence.
作者
马乐民
徐小乐
刘明亮
MA Lemin;XU Xiaole;LIU Mingliang(Tianjin Institute of Geotechnical Investigation Surveying,Tianjin 300191,China)
出处
《施工技术》
CAS
2018年第A04期1466-1469,共4页
Construction Technology
关键词
小净距隧道
浅埋段
地表沉降
监控量测
数值模拟
small spacing tunnel
shallow-buried
ground subsidence
monitoring measurement
simulation