Construction Technology of Vertical Freezing Reinforcement of Shield Launching End Wall
下载PDF
导出
摘要 盾构始发与接收是盾构隧道施工的关键,为了保证盾构机进洞与始发施工安全,需要对盾构始发端头的土体加固。以苏通GIL综合管廊工程实例,研究了盾构始发施工垂直冷冻加固的冻结方案设计与施工技术要点,并探讨了施工应注意的事项。实测结果得到冻结壁交圈时间为22d,达到设计厚度时间为35d,冻结壁平均温度在-15℃以下,验证了冷冻加固法在盾构始发工程上的可行性。 Shield launching and receiving are the key points in process of shield tunnel construction.In order to ensure the shield launches safely,the soil around the tunnel shield-launching end must he reinforced.This paper took Sutong GIL comprehensive pipe corridor project as an example,studied the design of freezing plan and key technologies of shield launching construction,and the points for attention in construction were put forward.Test results show that the closure time of freezing wall is 22 days,reaching the designed thickness in the 35 days,and the average temperature of freezing curtain is below-15℃.The actual engineering practices prove the feasibility of freezing reinforcement method in the construction of shield launching.
作者 陆东生 陈鹏 姚之威 白坤 黄云天 LU Dongsheng;CHEN Peng;YAO Zhiwei;BAI Kun;HUANG Yuntian(State Grid Jiangsu Electric Power Co.,Ltd.,Nanjing,Jiangsu 210024,China;China Railway 14 Bureau Group Shield Engineering Co.,Ltd.,Nanjing,Jiangsu 211800,China;School of Mechanical and Electrical Engineering,Central South University,Changsha,Hu'nan 410083,China)
出处 《施工技术》 CAS 2018年第A04期1477-1480,共4页 Construction Technology
关键词 盾构 土体加固 垂直冷冻 施工技术 shields soil reinforcement vertical freezing construction
  • 相关文献

参考文献7

二级参考文献44

共引文献396

同被引文献38

引证文献5

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部