期刊文献+

综合管廊上跨既有地铁隧道顶进技术研究 被引量:9

Study on Jacking Technology of Utility Tunnel Crossing Above the Existing Subway Tunnel
下载PDF
导出
摘要 北京城市副中心行政办公区政通东路综合管廊从既有地铁6号线盾构区间上方穿过,具有'大断面、浅覆土、近距离'的特点,施工难度和风险较大。经过理论分析和数值模拟,采用'顶进穿越、卸一还一、土体加固'的处理技术,减弱了上方土体开挖产生的卸载效应导致既有盾构隧道出现隆起变形的影响,从而保证了既有地铁区间结构的稳定性和地铁列车的正常营运。 Utility tunnel of Zhengtong East Road in the secondary city center of Beijing crossing above the shield interval of the existing subway line No.6 with the characteristics of large cross section,shallow covering soil,close range,the construction is difficult and risky.Through theoretical analysis and numerical simulation,the technical measures including jacking method,weighing,soil reinforcement are used,which decrease the effect on the existing subway tunnel due to excavation unloading,the stability of the existing subway tunnel structure and the normal operation of subway are ensured.
作者 毕成双 BI Chengshuang(Shanghai Municipal Engineering Design Institute(Group)Co.,Ltd.,Shanghai 200092,China)
出处 《施工技术》 CAS 2019年第17期89-92,共4页 Construction Technology
关键词 综合管廊 地铁 竖向变形 顶进 数值模拟 utility tunnel subways vertical deformation jacking simulation
  • 相关文献

参考文献5

二级参考文献34

共引文献48

同被引文献57

引证文献9

二级引证文献62

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部