摘要 以水电站库区取水对发电影响分析为研究对象,从三种不同思路给出取水对下游发电损失量计算模式,并进行对比分析;以浙江省某小型河道水力枢纽库区内取水纠纷为案例,定量分析水电站库区取水对下游发电的影响,提出的分析方法可为类似的水事纠纷调解提供技术支持。 By taking the impact of water drawing from reservoir area for hydropower station on its power generation as the study object,the mode of calculation on the power loss of downstream hydropower station because of the impact of the water drawing is given with three different concepts,and then a comparative analysis is given. Furthermore,based on the case of a water dispute caused by the water drawing from the reservoir area of a small sized hydropower project on river channel,the impact of water drawing from reservoir area for hydropower station on the downstream power generation is quantitatively analyzed; from which the analysis method proposed herein can provide a technical support for settling the similar water dispute.
出处 《水利水电技术》 CSCD 北大核心 2014年第4期130-133,共4页 Water Resources and Hydropower Engineering
基金 国家自然基金项目(51079130) 浙江省重点科技创新团队(2010R50035)
关键词 取水纠纷 发电影响 计算模式 水电站 water disputes impact on power generation calculation model hydropower station
  • 相关文献

参考文献7

二级参考文献31

共引文献132

同被引文献7

引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部