期刊文献+

南水北调中线一期工程总干渠高地下水位渠道设计主要问题及对策措施 被引量:7

Main problems from design of channel with high groundwater level for main canal of Phase I of Mid-Route of South-to-North Water Transfer Project and their countermeasures
下载PDF
导出
摘要 高地下水位的处理是南水北调中线一期工程总干渠渠道设计中的主要技术问题。对挖方较深和渠基透水性较强渠段,这一问题尤为突出。本文以总干渠陶岔至沙河南段、黄河北至羑河北段的部分渠段为例,对高地下水位渠道存在的主要问题、处理方法及原则进行了分析,对南水北调中线一期工程总干渠所涉及的主要对策措施进行了介绍,主要包括:(1)逆止阀自流内排;(2)水泵抽排;(3)换填结合排水法。 The high groundwater level is a main problem to be treated with during the design of the channel for the main canal of the phase I of the Mid-Route of the South-to-North Water Transfer Project and it is particular prominent for those channel sections to be deeply excavated or deal with the foundations of strong permeability. By taking the part channel sections of the main canal from Taocha-section to the section of the south of Shahe River and the section of the north of the Yellow River to the section of the north of Youhe River as the study cases,the main problems from the channel with high groundwater level and the treatment methods with their principles are analyzed herein,and then the main countermeasures related to the construction of the main canal of the Phase I of the Mid-Route of the South-to-North Water Transfer Project are described as well,which mainly include(1) internal drainage with free-flow through non-return valve;(2) pumping drainage;(3) earth replacement combined with the relevant methods for drainage.
出处 《水利水电技术》 CSCD 北大核心 2014年第11期41-44,共4页 Water Resources and Hydropower Engineering
关键词 南水北调 高地下水位 渠道 设计 South-to-North Water Transfer Project high groundwater level channel design treatment measures
  • 相关文献

同被引文献90

引证文献7

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部