本文以沙雅县2015年支、斗渠防渗改建工程为实例,针对该老渠改建工程存在的灌溉用水、施工用水、灌溉停水期施工用水的矛盾,提出合理工序安排以及具体实施过程,为同类工程提供参考实例。
In the paper,2015 Shaya County branch and lateral canal anti-seepage rebuilt project is adopted as an example.Rational procedures and concrete implementation process are proposed aiming at contradictions in old canal rebuilding project,such as irrigation water,construction water,and construction water for irrigation stop period,thereby providing reference example for similar projects.