摘要 针对泡子沿水库坝体有水浸现象,水库淤积严重,水库蓄水能力降低,下游坝脚处多处产生渗漏现象等险情,通过地质勘察找出原因,通过两种方案比较,选择高压喷射灌浆方案形成覆盖层的方式处理渗漏问题,旨在为相关水利工程提供参考。 Since Paoziyan Reservoir surfers from the following risks such as water seepage phenomena on the dam body,serious reservoir sedimentation,reservoir water storage capacity reduction,multiple seepage phenomena at the root of downstream dam. Reasons are discovered through geological survey. Two plans are compared. High pressure jet grouting plan should be selected for treatment of seepage problem on the covering layer,thereby providing references for related water conservancy projects.
作者 刘成刚
出处 《水资源开发与管理》 2016年第6期27-29,共3页 Water Resources Development and Management
关键词 坝基渗漏 工程地质 方案 泡子沿水库 dam foundation seepage engineering geology plan Paoziyan Reservoir
  • 相关文献

参考文献5

二级参考文献2

  • 1折学森.软土地基沉降计算[M].北京:人民交通出版社,1999..
  • 2武汉水利电力学院.土力学与岩石力学[M].北京:水利水电出版社,1982..

共引文献4

同被引文献9

引证文献2

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部