7起500kV进口变压器验收局放试验异常的分析

Analysis of abnormal condition in acceptance tests for imported 500 kV transformers
原文传递
导出
摘要 介绍了近年来华东电网500kV进口变压器现场验收试验中发生的7起异常情况。分析表明,其原因大多为制造质量问题。对此,提出了必须从设备招标采购、设计联络会、工厂监造与出厂试验、现场安装与验收试验等环节加强变压器的全过程管理和及时分析处理。 The abnormal results of 7 partial discharge tests for acceptance occurred in recent years of 500 kV transformers imported by East China Electric Power Network were introduced. The analysis showed that the main reasons were concerned largely in manufacturing quality. Therefore the whole process management must be reinforced in such aspects as bidding and purchasing of equipments, holding design liaison meeting, factory manufacturing supervision and delivery test, field installation and acceptance test. Analysis and treatment must be also carried out timely at the same time.
作者 钱之银 殷可
机构地区 国电华东公司
出处 《华东电力》 北大核心 2003年第9期31-32,共2页 East China Electric Power
关键词 500KV变压器 局部放电 试验 绝缘筒 绝缘纸板 进口产品 imported 500 kV transformer field acceptance induced partial discharge test oil chromatographic analysis
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部