摘要
为提高抽水蓄能电站防水淹厂房能力,减少水淹厂房损失,对电站上水库进/出水口设置快速闸门的方案进行研究。采用闸阀式快速闸门的方案切实可行,可提高闸门防事故扩大的能力,提高闸门闭门可靠性,为抽水蓄能电站防水淹厂房设计提供新思路。
In order to improve the capacity of preventing powerhouse flooding accident of pumped-storage power station and reduce the loss of powerhouse flooding, the research on setting up stop gate at upper reservoir inlet/outlet of pumped-storage power station is carried out. The scheme of using gate-valve stop gate is feasible, which can improve the capacity of accident prevention of gate and the reliability of gate closing. The scheme of setting up stop gate provides a new idea for the design of preventing powerhouse flooding for pumped-storage power stations.
作者
钟全胜
童慧
蒋立新
任鑫
钟聚光
ZHONG Quansheng;TONG Hui;JIANG Lixin;REN Xin;ZHONG Juguang(PowerChina Zhongnan Engineering Corporation Limited,Changsha 410014,Hunan,China;Hunan Pingjiang Pumped Storage Power Station Co.,Ltd.,Pingjiang 414500,Hunan,China)
出处
《水力发电》
北大核心
2019年第3期90-94,共5页
Water Power
关键词
水淹厂房
事故闸门
快速闸门
抽水蓄能电站
powerhouse flooding
emergency gate
stop gate
pumped-storage power station